India Hadi Ya project DCS system being into debug , factory acceptance phase
Release time:2015-10-25 Clicks:1163
Since the instrument shares borne by the company in India Hadi Ya station automation project I & C part of the first 30-million unit DCS system has entered the system commissioning, factory acceptance phase.
India Hadi Ya project is two 300,000 unit project by Shanghai Electric as a general contractor . Hadi Ya project is the second phase of the project , a project for the Indian Chang Delap project , the same as two 300,000 unit project . Chang is currently a project first set Delap 300,000 units and power generation is about to enter the stage . According to the contract, the first set of 300,000 units哈迪亚project DCS system , the system will be factory acceptance in July , August shipment to India site .
Currently station automation company engineering and technical personnel already do the preparatory work , we are now entering the nervous system and methodical commissioning , ensure that the project well done